When will it arrive – Part 2

A quick update on the “when will it arrive” question. As the main pressure hull nears completion we have some better estimates of the work remaining. Figure one month for moving the hull from the hanger in to the water, one month for ballasting and fitting running gear, one month for sea trails and debugging, one month to sail to California. This puts the potential delivery time around April (give or take a month).

P.s: Happy new year!